Cape Wind | Cape Wind - first planned US offshore wind farm

"As advisors, their work has been thorough, thoughtful, timely and professional. In addition, they have been able to draw on wide range of skill sets within the K2 Management organization to provide insights and advice on how to avoid numerous potential concerns before they are encountered. In summary, I can highly recommend the services of K2 Management".

Client testimonial

From 2011 to 2015  we were assigned by Cape Wind Associates as project management contractor on the Cape Wind project in the US.

The planned project size was 468 MW and K2 Management's scope of work included:

Cape Wind

K2 Management personnel have ably represented the owner’s interest in many technical aspects of the project including the foundation design, certification and tendering process, contributed to installation procedures and vessel selection and offshore sub-station structural engineering. In addition, K2 Management personnel are managing much of the remaining design. Lastly, K2 Management is providing full planning and scheduling services for all aspects of the projects.

Over the past several years, K2 Management has played a crucial role in the continued success of the Cape Wind Project. As advisors, their work has been thorough, thoughtful, timely and professional. In addition, they have been able to draw on wide range of skill sets within the K2 Management organization to provide insights and advice on how to avoid numerous potential concerns before they are encountered.

In summary, I can highly recommend the services of K2 Management.

Craig Olmsted
Vice President – projects

You might also be interested in

Macquarie | Technical due diligence on acquisition of Green Investment Bank

A consortium led by Australian bank, Macquarie, has agreed to purchase the UK’s Green Investment Bank today in a £2.3bn GBP deal. K2 Management led the technical due diligence on the transaction on behalf of Macquarie after being appointed in 2016.

London Array | Cables for world's largest offshore windfarm

For more than two years K2 Management supported London Array Ltd develop the world's largest wind farm, 630 MW London Array outside the coast of UK.  We also later worked as Lender’s Engineer for Masdar and Tokyo Mitsubishi Bank prior to their investment in the project.

 

Installation Manager on London Array

From August 2010 to December 2012 we supplied the project with an onsite Installation Manager for the cable installation. Our scope of work included:

In details:

  • High level planning with wind farm operations team
  • Detailed planning of work
  • Method Statements review and approval
  • Risk Assessments review and approval
  • Control of vessel and cable installation equipment inspection activities
  • On site HSE review related to cable contractors activities
  • Optimisation of on-site cable installation sequencing with installation contractor
  • Contractor vetting (as required for additional services)
  • Daily coordination of activities
  • Tool Box meetings
  • Documentation Control
  • Daily Reporting
  • Liaison between port captain and vessels

July 2009 to Jan 2010:

Lender’s Engineer (working in partnership with SgurrEnergy) for Masdar and Tokyo Mitsubishi Bank:

  • Review of technical information
  • Review of selected contractors and contracts
  • Review of project schedule Review of installation process.

Gode Wind II | Offshore Project Management

From 2009 to 2011 K2 Management helped PNE Wind develop the 240 MW offshore Gode Wind II project, located in the German North Sea.

John Laing | Projects in Sweden

K2 Management is proud to assist John Laing, a leading international infrastructure investor and asset manager, on an ongoing basis identifying investment opportunities in the wind energy sector.

Yeongyang Wind Farm | 59 MW onshore in South Korea

 

Luhanka, Latamäki | Securing wind energy in Finland

K2 Management has been an important partner for local developer Ilmatar in terms of closing the contract with wind turbine manufacturer Vestas for the Luhanka, Latamäki site. 

ESB Wind Development | CFD and noise modelling

Development support and energy yield assessment for 120 MW Grousemount Wind Farm incorporating CFD and noise modelling

i Squared Capital | Technical evaluation of onshore wind portfolio

Rapid technical evaluation for acquisition of Viridian's 225 MW onshore Irish wind farm portfolio, we undertook site inspections, identified missing documents and provided a summery report for each project,

Contour Global | O&M service setup for Latin American wind portfolio

K2 Management was engaged by investor, Contour Global, based in USA, to deliver support in moving from a basic O&M set up to a full O&M support structure for a wind portfolio in Latin America.

Asset Management,Danish wind farm | Technical due diligence turbine inspection

Appointed Encavis in early 2018, K2 Management was tasked with a wind turbine inspection as part of a wider technical due diligence review.

Lender’s technical advisor on world’s biggest offshore wind farm

Joint venture partners, SSE and Equinor, appointed the K2 Management team as Lender’s Technical Advisor to Dogger Bank Wind Farm A and B – two out of three phases that combine to make the largest offshore wind development in the world. 

Owner’s Engineer on Octopus Investment’s Onshore Wind Project in Finland

Octopus Investments engaged K2 Management in an Owner’s Engineer role for Project Otso, an onshore wind project located in forested terrain in Finland. The project consists of two wind farms, Saunamaa and Suolakangas, comprised of 17 V150-4.2 MW WTGs.   